[Its-generator-contacts] FW: 4/7 Generator Load Transfer Test

Mitch Gans mgans at fsu.edu
Fri Mar 25 09:44:01 EDT 2022


Am following up on this discussion from March 4.

At the moment, we only have a generator load transfer test scheduled for 8:00 am on Thursday, April 7, 2022. This is so we can confirm that the monthly switch from Chiller #2 to Chiller #1 the day before will produce the same effect during the load transfer test as it did after switching from Chiller #1 to Chiller #2 the previous month, i.e. the chillers did not switch as a result of the generator test.

Will there be continued need for generator testing for the RTCC, and/or when may we expect that?

Thanks,

Mitch

RCC @ FSU now recycles can rings<https://rcc.fsu.edu/news/rcc-partners-cimes-and-engineering-recycle-can-rings>

[cid:image001.jpg at 01D8402C.DA91B330]

Mitch Gans
Florida State University
2035 E. Paul Dirac Drive
Tallahassee, FL 32306-2760
mgans at fsu.edu<mailto:mgans at fsu.edu>
Sliger Data Center: (850) 644-8555
Cell: (850) 591-6193
Fax: (850) 644-8722

From: Mitch Gans
Sent: Friday, March 4, 2022 9:18 AM
To: William Quarles <bquarlesiii at admin.fsu.edu>; its-generator-contacts at lists.fsu.edu; Shawn Whitman <shawn at aw-gc.com>; Jim Chason (jim at aw-gc.com) <jim at aw-gc.com>; Suber, Jeff <jeff.suber at siemens.com>; Trey Gossett <tgossett at admin.fsu.edu>; Paul Van Der Mark <pvandermark at fsu.edu>; Alexander Birkovsky <abirkovsky at fsu.edu>; James Ward <tward at fsu.edu>
Cc: Steven Hall <schall at admin.fsu.edu>; Michelle Taylor <taylorm at leoncountyfl.gov>
Subject: RE: 4/7 Generator Load Transfer Test

10-4, thanks, Biff.

Mitch

RCC @ FSU now recycles can rings<https://rcc.fsu.edu/news/rcc-partners-cimes-and-engineering-recycle-can-rings>

[cid:image001.jpg at 01D8402C.DA91B330]

Mitch Gans
Florida State University
2035 E. Paul Dirac Drive
Tallahassee, FL 32306-2760
mgans at fsu.edu<mailto:mgans at fsu.edu>
Sliger Data Center: (850) 644-8555
Cell: (850) 591-6193
Fax: (850) 644-8722

From: William Quarles <bquarlesiii at admin.fsu.edu<mailto:bquarlesiii at admin.fsu.edu>>
Sent: Friday, March 4, 2022 9:15 AM
To: Mitch Gans <mgans at fsu.edu<mailto:mgans at fsu.edu>>; its-generator-contacts at lists.fsu.edu<mailto:its-generator-contacts at lists.fsu.edu>; Shawn Whitman <shawn at aw-gc.com<mailto:shawn at aw-gc.com>>; Jim Chason (jim at aw-gc.com<mailto:jim at aw-gc.com>) <jim at aw-gc.com<mailto:jim at aw-gc.com>>; Suber, Jeff <jeff.suber at siemens.com<mailto:jeff.suber at siemens.com>>; Trey Gossett <tgossett at admin.fsu.edu<mailto:tgossett at admin.fsu.edu>>; Paul Van Der Mark <pvandermark at fsu.edu<mailto:pvandermark at fsu.edu>>; Alexander Birkovsky <abirkovsky at fsu.edu<mailto:abirkovsky at fsu.edu>>; James Ward <tward at fsu.edu<mailto:tward at fsu.edu>>
Cc: Steven Hall <schall at admin.fsu.edu<mailto:schall at admin.fsu.edu>>; Michelle Taylor <taylorm at leoncountyfl.gov<mailto:taylorm at leoncountyfl.gov>>; William Quarles <bquarlesiii at admin.fsu.edu<mailto:bquarlesiii at admin.fsu.edu>>
Subject: RE: 4/7 Generator Load Transfer Test

Thanks Mitch, I will need to schedule one before that to see if we have corrected the issue in the RTCC.  I'll give ample warning and will schedule only after talking to you.  Biff

W.S. (Biff) Quarles, III  -   Sr. Construction Project Manager
Florida State University  -  Facilities - Construction
Mendenhall A - Suite 107-B  -  Tallahassee, FL  32306-4153
Cell (850) 694-2454
bquarles at fsu.edu<mailto:bquarles at fsu.edu>   |    www.facilities.fsu.edu<http://www.facilities.fsu.edu>

From: Mitch Gans <mgans at fsu.edu<mailto:mgans at fsu.edu>>
Sent: Friday, March 4, 2022 9:12 AM
To: its-generator-contacts at lists.fsu.edu<mailto:its-generator-contacts at lists.fsu.edu>; William Quarles <bquarlesiii at admin.fsu.edu<mailto:bquarlesiii at admin.fsu.edu>>; Shawn Whitman <shawn at aw-gc.com<mailto:shawn at aw-gc.com>>; Jim Chason (jim at aw-gc.com<mailto:jim at aw-gc.com>) <jim at aw-gc.com<mailto:jim at aw-gc.com>>; Suber, Jeff <jeff.suber at siemens.com<mailto:jeff.suber at siemens.com>>; Trey Gossett <tgossett at admin.fsu.edu<mailto:tgossett at admin.fsu.edu>>; Paul Van Der Mark <pvandermark at fsu.edu<mailto:pvandermark at fsu.edu>>; Alexander Birkovsky <abirkovsky at fsu.edu<mailto:abirkovsky at fsu.edu>>; James Ward <tward at fsu.edu<mailto:tward at fsu.edu>>
Subject: 4/7 Generator Load Transfer Test


The next Sliger Building Generator Load Transfer Test will be conducted at 8:00 am on Thursday, April 7, 2022.

This notification serves as a scheduling reminder to interested parties at FSU Facilities, Research Computing Center, et al.
Mitch

RCC @ FSU now recycles can rings<https://rcc.fsu.edu/news/rcc-partners-cimes-and-engineering-recycle-can-rings>

[cid:image001.jpg at 01D8402C.DA91B330]

Mitch Gans
Florida State University
2035 E. Paul Dirac Drive
Tallahassee, FL 32306-2760
mgans at fsu.edu<mailto:mgans at fsu.edu>
Sliger Data Center: (850) 644-8555
Cell: (850) 591-6193
Fax: (850) 644-8722
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.fsu.edu/pipermail/its-generator-contacts/attachments/20220325/36eee1ec/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.jpg
Type: image/jpeg
Size: 7858 bytes
Desc: image001.jpg
URL: <http://lists.fsu.edu/pipermail/its-generator-contacts/attachments/20220325/36eee1ec/attachment.jpg>


More information about the Its-generator-contacts mailing list